EPC Work for Application of Digital Oil Field (DOF) Technology on Brownfield Towers in ZK Field

EPC Work for Application of Digital Oil FieldADNOC Offshore awarded Prestigious DOF Project to CAE in 2019 for Lower Zakum Offshore Oil Field.

The Project involved vast Engineering, Procurement, Barge Services along with Site execution till Commissioning and Handover.

The Scope of work involves Replacement of existing Manual Choke/Diverter/ DBB Valves with motor operated valves. Installation of CCTV system and all associated RTU, Telecom, Structural, Electrical Modification works on 21 WHT Platforms. Replacement of existing ESD RTU, SCADA at Super Complex, and integrate all signals from 21 DOF Platforms, and 41 Non DOF Platforms.

UZ Switchgear Replacement Project – EPC Works

UZ Switchgear Replacement ProjectADNOC Offshore awarded the Project to CAE in 2019 for Upper Zakum Offshore Oil Field. The locations are GTP, WIP, PGP, NSP, WSP and SSP at Upper Zakum Offshore.

The Project involves Engineering, Procurement, Marine Transportation Services along with Site execution till Commissioning and Handover.

The scope of work involves replacement of existing switchgear with new Switchgear and Retrofit of existing switchgears with new components and adding new IPCMS. Also, the scope involves associated cabling, Structural, Instrumentation, HVAC and F&G works.